Lake Fan: Town and DES have 30 days to respond…if they have any questions, you will have 30 days to rep,y to that….then they have another 30 days to reply to you again….so, plan ahead and expect it to take several months.

For our recent project, we had submitted plans in November and I believe I had DES approval in Jan.

Also…to the original poster…if your structure is out of the 250 and it’s just driveway, you may be able to avoid shoreland permitting, but check with the town and survey engineer on that .