A few additional thoughts as we’ve recently gone through the full state and town permitting process:
- Full survey and topographical site plan is step 1 so you know what you actually have and where you can actually build per property boundaries, wetlands, slopes, possible septic locations, well, etc
- NHDES and town Shoreland permit process requires a full site plan AND proposed building footprint with all pervious/impervious areas, so you will need some aspect of that from the Architect (you don’t need full building permit plan, but do need the foundation and surrounding elements like patios, driveway, etc)
- Your surveyor should be able to help manage that permit process for you, but you’ll need an architect or designer for the house footprint parts

Hope that helps…