Quote:
Originally Posted by Riviera View Post
It is in Alton.

Section 1.06 of the Site Plan Review Regulations specifically requires that any required ZBA approvals must be obtained, and submitted as part of the Planning Board application, prior to the PB application being deemed complete. The PB will take no action until a complete application has been submitted. There are, however, provisions that would allow for a conceptual hearing prior to a ZBA approval.

Long story short, in this instance, they need a ZBA approval before they can submit a formal application the PB.

I think Dennis got it right!
Then in this case the PB meeting to hear the application needs to be postponed because, to all intents and purposes, there's nothing to hear. I have to wonder if the applicants will request a continuance for a month or more until they can get what they need from the ZBA?

I do know that the applicants did mention something about amending their site plan such that they wouldn't require as many variances. It will be interesting to see what they'll do to make that a possibility.