This is not something you would need a variance for under the current language of the Shoreland Protection Act. If your project involves expansion of the structure within the 50 ft setback then there needs to be something about the project that makes it more nearly conforming to the overall intent and purpose of the Act (see RSA 483-B:11). In essence you should include something in your proposal to mitigate for the expansion. Things that can be done include upgrading the septic system, improving the the vegetated buffers, or improving stormwater management. If no portion of your expansion will be within the 50 ft setback, then it is reviewed as a regular application with no special requirements.
D. Forst
Shoreland Section Supervisor
NH DES Land Resource Management
|